Loft Conversion in Banbury, Oxfordshire

  • Location: Banbury, OX16
  • Project Type: Rear dormer loft conversion with two bedrooms and a bathroom, new staircase, roof renewal and first-floor bathroom renovation
  • Duration: Approximately 18 weeks on site (May to September 2025)
  • Role: Principal Contractor (Full Project Delivery)

Introduction

This loft conversion in Banbury turned the empty roof space above a family home on Bloxham Road into two bedrooms and a bathroom, reached by a new staircase, with the existing first-floor bathroom renovated in the same programme and the whole roof renewed while the scaffold was up.

Chris first got in touch in December 2024. We went to look at the loft the next day, and because Chris had not worked with us before, we put him in touch with a Banbury client whose extension we had finished the year before, so he could see our work and hear about us from someone who had lived through a project with us. A leak in the front bedroom that winter pushed the start back a few months. By May 2025 the structural engineer's drawings and calculations were complete, the contract was signed, and the scaffold was booked.

The Brief: Two Bedrooms and a Bathroom in the Roof

The family needed more bedrooms without moving house. The brief was simple to state and demanding to deliver: two bedrooms and a bathroom in the roof, a permanent staircase to reach them, a full renovation of the existing first-floor bathroom, and all of it delivered by one team and signed off by Building Control.

A loft conversion is often described as a roofing job with a room at the end. This one shows why it is a whole-house project. The new staircase changed the first-floor layout. The new bathroom needed drainage and ventilation routed through the floors below. Fire safety for a house with an extra storey affects the existing stair and doors, not only the loft. Doing the first-floor bathroom at the same time meant the plumbing, tiling and finishes were sequenced once, and the family put up with the disruption once.

Getting the Paperwork Right Before the Scaffold Went Up

The structural design came from a structural engineer, with a full calculation package for the steel beams, the new floor and the dormer roof, and the project went to Cherwell District Council's Building Control as a full-plans application, so the design was checked on paper before anything was built.

Chris wanted the money side settled before work started, and so did we. The stage payments were agreed before the contract was signed: a deposit on starting, then payments at structural completion, first fix, second fix and completion. He also asked us to confirm exactly what the roof price included, which we did in writing, and he chose and supplied the internal doors, the bathroom fittings and the bathroom tiles himself, sending over his own sketches of the two bathroom layouts for us to work from. When he later wrote that we "gave a clear quote and explained exactly what was included", this is what he meant.

Scaffolding and the Temporary Roof

On most of our loft conversions we put a temporary roof over the scaffold, so that once the tiles come off the house stays dry whatever the weather does. It costs more than a standard scaffold, and we only leave it out when a client's budget is very tight and they understand the risk. We have used the same scaffolding company for years, and they went up on Bloxham Road on 13 May 2025.

IMG 0616
IMG 0629

Strip-Out and the New Roof Structure

The work began by stripping out the existing roof so that the new structure could be formed. Taking the roof off first gives clear access and lets the new work be set out accurately rather than squeezed around what was there.

Steel beams went in to carry the new floor and the dormer, the loft floor was rebuilt as a structural floor able to take two bedrooms and a bathroom, and the new roof frame was built to the engineer's drawings, with high-level collars below the ridge and the rafters fixed to the wall plates with Simpson Strong-Tie clips. By the middle of June the structural stage was complete.

A Rear Dormer Loft Conversion with Velux Windows to the Front

The dormer runs across the rear of the house and is what gives the two bedrooms and the bathroom their full-height floor area. Velux windows were fitted to the front slope, so from Bloxham Road the house looks as it always did, while the new rooms take their daylight and their outlook from the windows in the dormer at the back.

A New Roof Over the Whole House

The new roof over the dormer and the altered slopes was finished with new breathable membrane, battens and tiles, new fascias and new guttering. On the slopes that were not altered, the original tiles were lifted, the roof was re-felted and re-battened, and the tiles were put back, with new fascia boards and gutters to match. The result is a roof that is new underneath from end to end and still looks like one roof from the street. While the scaffold was up, the front bay was rendered too, which is the cheapest time to do it.

IMG 1097
IMG 2073

Insulation, Staircase and the Loft Rooms

The roof was insulated to current standards, which takes height from the finished rooms and is one reason the frame and the floor were designed as one. A permanent staircase was installed to reach the loft. Its position decides the layout on both floors, so it was fixed early and built to meet Building Regulations for headroom and safe escape. The converted space was then divided into two bedrooms and a bathroom, with drainage, water, ventilation and waterproofing brought up to roof level and coordinated with the structure beneath.

IMG 1097
IMG 2689

The First-Floor Bathroom, Renovated at the Same Time

Rather than leave the house with a new bathroom above a dated one, the existing first-floor bathroom was stripped and refitted in the same programme, to Chris's layout and with the fittings and tiles he had chosen.

Building Control Inspections and Sign-Off

The inspectors from Cherwell District Council visited during construction. In July, before they would pass the roof structure, they asked for photographic evidence of the dormer roof, specifically the high-level collars and the clips fixing the rafters to the wall plates. We had built it to the engineer's specification, so the photographs and the specification were sent over and the work was signed off.

That is what inspection is for, and it is why the completion certificate matters. It was handed over with our own completion paperwork and guarantee in October 2025. Solicitors ask for it when a house is sold or remortgaged, and a loft conversion without one can hold up a sale for months.

How the 18 Weeks Ran

The scaffold went up on 13 May 2025 and the roof came off. The steels, the new floor and the dormer frame were in by mid-June, the roof covering and windows followed, and the first fix of plumbing and electrics went in behind them. Building Control's structural queries were answered in July while the plastering started, and the staircase, the two bathrooms, the second fix and the decoration ran through August into September. The finished loft was handed over in the middle of September, four months after the scaffold arrived.

The Result

Two bedrooms and a bathroom where there was a loft, a renovated first-floor bathroom, a new staircase, a renewed roof over the whole house, and a complete set of Building Control approvals. Even the neighbours noticed: one of them, a few doors along on the same road, has since asked us to look at their own loft.

IMG 2629
IMG 2688
IMG 2690
IMG 2691

Client Feedback

We honestly couldn't be happier

DKM Builders have just finished our loft conversion and we honestly couldn't be happier. From the start, they gave us a clear quote and explained exactly what was included. Yoti and the team were on site every day, working hard and always willing to suggest ideas or sort out any problems that came up. The quality of the work is excellent, and even our neighbours have commented on how good it looks. Building work can be stressful, but having a team with such a strong work ethic and friendly attitude made the whole thing much easier than we expected. We're really pleased with the end result and have already recommended DKM to friends.

Chris, Banbury

DKM Builders Approach

One team took this loft conversion from a stripped roof to a signed-off, decorated home: structure, roof, windows, staircase, plumbing, electrics, bathrooms and finishes, with the engineer's design followed to the letter and Building Control inspections booked at every stage. Chris had one point of contact throughout, a clear quotation and payment schedule before work started, and the certificate at the end. That is how we run every loft conversion, in Banbury or anywhere else in Oxfordshire.

Loft Conversions in Banbury: Questions We Are Asked

Do you need planning permission for a loft conversion in Banbury?

Often not. A rear dormer with roof windows to the front usually falls within permitted development, provided the house is not in a conservation area and the added roof space stays within the national limits. Every loft conversion that creates rooms needs Building Regulations approval, whatever its planning status. Our guide to permitted development explains the limits.

How long does a loft conversion take?

This one took about 18 weeks from the scaffold going up to handover, including the roof renewal and the second bathroom. A simpler rear dormer loft conversion typically takes 8 to 12 weeks on site.

Who inspects a loft conversion in Banbury?

Cherwell District Council's Building Control, or a registered building control approver if the homeowner prefers. On this project the council checked the drawings in advance and inspected the structure, insulation, fire safety, staircase and drainage as the work progressed.

Can we stay in the house during a loft conversion?

Usually, yes. The work comes in through the scaffold, and the house is only opened up when the staircase is cut in, so most of our loft conversion clients stay at home throughout.

Planning a Loft Conversion in Banbury or Oxfordshire?

If you are weighing up a loft conversion in Banbury, Bicester, Kidlington, Oxford or anywhere else in Oxfordshire, the useful first step is not a price per square metre but a look at the roof: its height, its structure and where a staircase could land. Send us photographs of the loft, an approximate floor measurement and any drawings you already have, and we will tell you what looks practical before anyone draws anything.

DKM Builders Oxford Ltd delivers loft conversions, extensions and full refurbishments across Oxford and Oxfordshire as Principal Contractor, with Building Control coordinated as part of every project.

Contact DKM Builders Oxford Ltd to discuss your loft conversion.

contact us

Ready to Start a Project?

Get in touch to arrange a professional consultation and explore how we can support your project from the outset.